Project: Shermnator   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:David Sherman   -  
Project:   Vans - RV-9A   -   VIEW REPORTS
Total Hours:538.25
Start/Last Date:Dec 12, 2020 - Jun 01, 2025
Engine:Lycoming O-320 D2A
 
Friendly URL: https://eaabuilderslog.org?s=Shermnator

Home or Last Project Picture

Nov 24, 2023     Aft fuselage complete - (8 hours)       Category: Fuselage
It is awesome to have an expert riveting buddy. Chris is fast and we almost don't even need to talk we are so in-tuned with each other when riveting. Shannon even helped out and fed rivets while Chris bucked and I had the hammer. 2 hours to rivet the whole thing together. All the open places are intentional as the forward bulkhead attaches to the center fuselage and the sides need flex for the longerons.


 